March 2008 Updates

Campus Wide Fire Alarm Upgrades

Building 2 Ceiling and conduits. February 2, 2007. Click to Zoom. Building 6 Plenum area and wiring. July 11, 2007. Click to Zoom. Building 46 More areas above drop ceilings. August 15, 2007. Click to Zoom. Building 9 Patch and paint. August 22, 2007. Click to Zoom.

About This Project

The Fire Alarm Upgrades project consists of engineering and designing a new system that complies with all current applicable standards and codes, communicates and integrates with other campus fire alarm systems and any potential future fire alarm related upgrades. The buildings being upgraded are 1, 2, 6, 9, 13, 25, 29, 41, 43 and 46. Due to good results, Buildings 67, 89 and 92 have been added to the Fire Alarm Upgrades for this year. There is also consideration on reprogramming the Fire Alarm System in Building 4. Last year, Buildings 7, 8 and 45 were completed.

Statistical Information

Construction start date:
April 19, 2007
Expected completion date:
Summer 2010
Construction Cost:
TBD
Total Project Cost: $1,900,000
Gross sq. footage:
643,860
Assignable sq. footage:
389,322
% of project complete:
85%

Progress of Major Construction Activities

  • All current Buildings are complete.
  • The additional Buildings 67, 89 and 92 are under review by the State Fire Marshal.
  • Buildings 89A will also be added.
  • Buildings 86, 86A, 86B, and 86C are also due to receive a new fire alarm system but not as part of this project.

Key/Critical Issues Currently Pending

  • Buildings 13, 29 & 43 pretesting are pending.
  • State Fire Marshal’s final inspection pending pretesting.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.