February 2008 Updates

Campus Wide Fire Alarm Upgrades

Building 46  Look above the drop ceiling. 7-17-2007. Click to Zoom. Building 1  New Fire Control Panel. 7-27-2007. Click to Zoom. Building 9  New Pull Station vs. Old Pull Station. 8-28-2007. Click to Zoom. Building 13  Abatement Activities. 12-19-2007. Click to Zoom.

About This Project

The Fire Alarm Upgrades project consists of engineering and designing a new system that complies with all current applicable standards and codes, communicates and integrates with other campus fire alarm systems and any potential future fire alarm related upgrades. The buildings being upgraded are 1, 2, 6, 9, 13, 25, 29, 41, 43 and 46. Due to good results, Buildings 67, 89 and 92 have been added to the Fire Alarm Upgrades for this year. There is also consideration on reprogramming the Fire Alarm System in Building 4. Last year, Buildings 7, 8 and 45 were completed.

Statistical Information

Construction start date:
April 19, 2007
Expected completion date:
Summer 2010
Construction Cost:
TBD
Total Project Cost: $1,900,000
Gross sq. footage:
643,860
Assignable sq. footage:
389,322
% of project complete:
85%

Progress of Major Construction Activities

  • All current Buildings, except for 13, 29 & 43, are complete.
  • The additional Buildings 67, 89 and 92 are under review by the State Fire Marshal.

Key/Critical Issues Currently Pending

  • Buildings 13, 29 & 43 are scheduled for pretesting.
  • After pretesting, the State Fire Marshal will be contacted for the final inspection.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.