September 2008 Updates

Building 3 - Seismic Upgrade & Renovation

One of eight Physics Labs is shown in this photo.  Classrooms and Labs are all fitted out with LCTI equip. Click to Zoom. Department of Chemistry boasts new casework, new fume hoods and each lab supports accessible usage. Click to Zoom. South Elevation facing Building #8 – New sunshades installed over newly installed Low-E glazed windows. Click to Zoom.

One of the sustainable features installed on this project.  View at courtyard facing northeast. Click to Zoom. New entry off of University Drive.  Lobby and corridor entrance looking south.  New exaggerated columns. Click to Zoom. Project scope included the installation of all new Men’s & Women’s restrooms throughout. Click to Zoom.

About This Project

Building 3 is one of the oldest buildings on the Cal Poly Pomona campus. This project will renovate approximately 72,000 gross square feet and includes installing new electrical, mechanical, plumbing and telecommunication services, new fire/life safety systems and upgraded energy efficient lighting. It also abates hazardous materials, replaces the existing roofing system and will include the installation of two new accessible elevators.

This $26.9 million project also consists of installing state-of-the-art Learning Centered Technology Initiative equipment in all instructional classrooms and classroom labs. The building’s original 1957 constructed exterior façade will undergo a rehabilitation that will include all glazing and window frame replacement with an energy efficient window system. An energy efficient air conditioning system will be installed.

Sustainability Benefits for this project include: a new window / low “e” glazing system, a connection to the campus chilled water system, an energy efficient lighting systems, a ‘cool-roof’ TPO system, an upgrade electrical service from the campus’ high voltage 12KV service, an efficient HVAC system, installation of exterior sunshades and the building’s men’s restrooms will be plumbed for a future retrofit of waterless urinals.

Statistical Information

Construction start date:
Sept. 25, 2006
Expected completion date:
Fall 2008
Construction Cost:
$18,790,000
Total Project Cost: $26,939,354
Gross sq. footage:
72,323
Assignable sq. footage:
46,810
% of project complete:
100%

Progress of Major Construction Activities

  • Classes begun on 9/25/08 as scheduled.
  • Construction Close-out of the main contract is being finalized.
  • All departments have moved into Building #3 as of 9/22/08.
  • Furniture and Equipment (Group II) is 99% delivered / installed / tested.

Key/Critical Issues Currently Pending

  • Finalize main contract close-out tasks.
  • File Notice of Completion with L.A. County
  • Implement campus support services for building occupancy (Housekeeping, FM maintenance, etc.)

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.