August 2008 Updates

Building 3 - Seismic Upgrade & Renovation

New exterior window systems with exterior concrete repainted – View from University Drive. Click to Zoom. Relandscaped new University Drive Entrance taken 9/5/08. Click to Zoom. New corridors with varying colored tile floor designs. Click to Zoom.

Newly installed Chemistry Lab Casework. Click to Zoom. New College of Science – Physics Labs with new student work tables. New College of ENV digital lab tables. Click to Zoom.

About This Project

Building 3 is one of the oldest buildings on the Cal Poly Pomona campus. This project will renovate approximately 72,000 gross square feet and includes installing new electrical, mechanical, plumbing and telecommunication services, new fire/life safety systems and upgraded energy efficient lighting. It also abates hazardous materials, replaces the existing roofing system and will include the installation of two new accessible elevators.

This $26.9 million project also consists of installing state-of-the-art Learning Centered Technology Initiative equipment in all instructional classrooms and classroom labs. The building’s original 1957 constructed exterior façade will undergo a rehabilitation that will include all glazing and window frame replacement with an energy efficient window system. An energy efficient air conditioning system will be installed.

Sustainability Benefits for this project include: a new window / low “e” glazing system, a connection to the campus chilled water system, an energy efficient lighting systems, a ‘cool-roof’ TPO system, an upgrade electrical service from the campus’ high voltage 12KV service, an efficient HVAC system, installation of exterior sunshades and the building’s men’s restrooms will be plumbed for a future retrofit of waterless urinals.

Statistical Information

Construction start date:
Sept. 25, 2006
Expected completion date:
Fall 2008
Construction Cost:
$21,053,750
Total Project Cost: $26,939,354
Gross sq. footage:
72,323
Assignable sq. footage:
46,819
% of project complete:
99%

Progress of Major Construction Activities

  • Certificate of Occupancy from our State Fire Marshal has been secured on Tues. 8/26/08.
  • Construction Close-out of the Main Contract is underway.
  • Departments have begun their move into Building #3 as of 9/5/08.
  • Furniture and Equipment (Group II) is approximately 95% delivered / installed / tested.
  • Networking equipment for the new voice/data system is installed.
  • Interior signage is 99% complete.
  • Building will be ready for Fall Quarter classes.

Key/Critical Issues Currently Pending

  • Finalize main contract close-out tasks.
  • File Notice of Completion with L.A. County
  • Implement campus support services for building occupancy (Housekeeping, FM maintenance, etc.)

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.