February 2008 Updates

Building 3 - Seismic Upgrade & Renovation

New exterior window systems; view facing west into courtyard. Click to Zoom. New exterior window systems with exterior concrete repainted; View from University Drive. Click to Zoom. Typical new classroom with new ceilings, new lighting, air conditioning and new cabinets. Click to Zoom.

New Chemistry Labs getting the fixed casework installed along with new ceilings, lighting, etc. Click to Xoom. New corridor architectural elements that will break up the long corridors. Click to Zoom. Another photo of a new Chemistry Lab coming on-line. Click to Zoom.

About This Project

Building 3 is one of the oldest buildings on the Cal Poly Pomona campus. This project will renovate approximately 72,000 gross square feet and includes installing new electrical, mechanical, plumbing and telecommunication services, new fire/life safety systems and upgraded energy efficient lighting. It also abates hazardous materials, replaces the existing roofing system and will include the installation of two new accessible elevators.

This $26.9 million project also consists of installing state-of-the-art Learning Centered Technology Initiative equipment in all instructional classrooms and classroom labs. The building’s original 1957 constructed exterior façade will undergo a rehabilitation that will include all glazing and window frame replacement with an energy efficient window system. An energy efficient air conditioning system will be installed.

Sustainability Benefits for this project include: a new window / low “e” glazing system, a connection to the campus chilled water system, an energy efficient lighting systems, a ‘cool-roof’ TPO system, an upgrade electrical service from the campus’ high voltage 12KV service, an efficient HVAC system, installation of exterior sunshades and the building’s men’s restrooms will be plumbed for a future retrofit of waterless urinals.

Statistical Information

Construction start date:
Sept. 25, 2006
Expected completion date:
Fall 2008
Construction Cost:
$21,053,750
Total Project Cost: $26,939,354
Gross sq. footage:
72,323
Assignable sq. footage:
46,819
% of project complete:
90%

Progress of Major Construction Activities

  • New HVAC, electrical and plumbing systems installation is approx. 90% complete.
  • Exterior installation of new windows, painting, hardscape, roof systems are 95% complete.
  • Installation of off-site utility connections are complete (chilled water, high voltage electrical, gas, fire water service and I & IT fiber)

Key/Critical Issues Currently Pending

  • Perform tube steel welding testing at all welded seam locations.
  • Transfer voice/data and fire alarm systems services from the two Lecture Rooms onto new Building #3’s main systems.
  • Begin HVAC equipment commissioning to support mechanical systems ‘start-up’ process.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.