Cal Poly Pomona

September 2007 Updates

Building 3 - Seismic Upgrade & Renovation

Building 3 rooftop. Click to zoom. Building 3 construction. Click to Zoom. Scaffolds. Click to zoom. Construction hallway. Click to zoom.

About This Project

Building 3 is one of the oldest buildings on the Cal Poly Pomona campus. It is located between Building 92 to the west and Building 8 to the east. This project will renovate approximately 72,000 gross square feet and includes installing new electrical, mechanical, plumbing and telecommunication services, new fire/life safety systems and upgraded energy efficient lighting. It also abates hazardous materials, replaces the existing roofing system and will include the installation of two new accessible elevators.

This $26.9 million project also consists of installing state-of-the-art Learning Centered Technology Initiative equipment in all instructional classrooms and classroom labs. The building’s original 1957 constructed exterior façade will undergo a rehabilitation that will include all glazing and window frame replacement with an energy efficient window system. An energy efficient air conditioning system will be installed.

Sustainability Benefits for this project include: a new window / low “e” glazing system, a connection to the campus chilled water system, an energy efficient lighting systems, a ‘cool-roof’ TPO system, an upgrade electrical service from the campus’ high voltage 12KV service, an efficient HVAC system, installation of exterior sunshades and the building’s men’s restrooms will be plumbed for a future retrofit of waterless urinals.

Statistical Information

Construction start date:
Sept. 25, 2006
Expected completion date:
Fall 2008
Construction Cost:
$21,053,750
Total Project Cost: $26,939,354
Gross sq. footage:
72,323
Assignable sq. footage:
46,819
% of project complete:
68%

Progress of Major Construction Activities

  • New HVAC, electrical and plumbing systems installation is approx. 55% complete.
  • 97% of new wall framing is complete.
  • Installation of chilled water lines on University Drive between Building 7 and Building 3 is 97% complete.
  • Installation of the new roofing is approximately 80% complete.
  • Off-site utility work for new electrical, storm drain and sanitary sewer work is approx. 80% complete.

Key/Critical Issues Currently Pending

  • Schedule Lecture Rm. work during Christmas Break with contractor to avoid any class schedule interruptions.
  • Coordinate the second high voltage electrical shutdown in Manhole #R (Tentative date is scheduled for 11/3/07).

30 Day Look Ahead of Major Activities

  • Continue with drywall installation at building interiors and prep for priming and wall painting.
  • Continue with rough-in utility work for the new HVAC, electrical and plumbing trades on both floors.
  • Complete exterior building painting.

Upcoming Utility or Other Interruptions

  • Schedule second electrical shut down for 8 buildings being serviced from Feeders #5 & #6.

Other Areas of Significance

  • NA at this time.