March 2009 Updates

Bldg. 24 & 25 HVAC Retrofit Upgrade

Building 25 - Newly added actuator at chilled water lines in mechanical room for loop/temperature control. Click to Zoom. Building 24 - Newly added  actuator at rehearsal area for noise control and to replace old pneumatics. Click to Zoom. Building 24 - New zone controllers at mixing boxes above hallway ceilings.  Programming in progress. Click to Zoom.
Building 25 - Previously installed [+/-36 months ago] zone controllers located in mechanical room. Click to Zoom. Building 25 - New chilled water pipes attached to existing.  Being assessed for additional seismic bracing. Click to Zoom. New Netook used by CPP HVAC personnel to monitor/adjust various HVAC systems across Campus. Click to Zoom.

About This Project

The scope of the Energy Efficiency HVAC Retrofit for Music Building 24 is to convert the constant volume, double duct, air handling unit, SA-3/RA-3, into a variable air volume (VAV), double duct air handling unit. With this approach, this air handling system will operate as a VAV system in that cold and hot air will not need to be mixed anymore, except when code minimum air flows are reached. Each zone will generally either call for heating or cooling, and the air flow to that zone will be varied to satisfy thermal need. The supply fan and return fan, provided with new variable frequency drives (VFDs) will slow down or speed up to deliver only the amount of air needed to satisfy load.

Statistical Information

Construction start date:
Nov 2008
Expected completion date:
April/May 2009
Construction Cost:
$525,000
Total Project Cost: $550,000
Gross sq. footage:
89,227
Assignable sq. footage addition:
47,225
% of project complete:
99%

Project Funding

  • Funding for this project is from the campuses Deferred Maintenance Budget, the S.C. Edison Energy Rebate Fund and the General Utility Budget Fund.

Progress of Major Construction Activities

  • All major activities complete with additional programming, adjustments at controllers, air-balancing and testing on-going.
  • Punch-list is in progress. Hallway ceiling has been reassembled with “access panels” installed for easy in future servicing. Touch-up is nearly complete.

Key/Critical Issues Currently Pending

  • Because of the age and condition of the existing system and the intricacies involved with upgrading such, there have been programming, calibrating, and air balancing challenges.
  • Punch-list is basically complete but will not be signed off as 100% until any remaining programming and air balancing concerns are worked out. Some related work scheduled to take place during this Easter weekend.

Upcoming Utility or Other Interruptions

  • None anticipated although additional controllers related work will be taking place by the energy management system/controls subcontractor during the weekend of April 18th and 19th.

Other Areas of Significance

  • NA at this time.