About This Project

The scope of the Energy Efficiency HVAC Retrofit for Music Building 24 is to convert the constant volume, double duct, air handling unit, SA-3/RA-3, into a variable air volume (VAV), double duct air handling unit. With this approach, this air handling system will operate as a VAV system in that cold and hot air will not need to be mixed anymore, except when code minimum air flows are reached. Each zone will generally either call for heating or cooling, and the air flow to that zone will be varied to satisfy thermal need. The supply fan and return fan, provided with new variable frequency drives (VFDs) will slow down or speed up to deliver only the amount of air needed to satisfy load.

Statistical Information

Construction start date:
Nov 2008
Expected completion date:
Jan 2009
Construction Cost:
$525,000
Total Project Cost: $550,000
Gross sq. footage:
89,227
Assignable sq. footage addition:
47,225
% of project complete:
10%

Progress of Major Construction Activities

  • Submittals have been approved. Environmental consulting and related site preparation work is nearly complete.

Key/Critical Issues Currently Pending

  • Materials delivery dates are being determined.

Upcoming Utility or Other Interruptions

  • Major shut-downs for Buildings 24 and/or 25 depend on materials availability. The hope is for these shut-downs to occur primarily during the upcoming Holiday Break.

Other Areas of Significance

  • NA at this time.