December 2011 Updates

Aliso Hall - Bldg. 23 ADA Restroom & 1st Floor Upgrade

View of Building 23 typical brick façade along University Drive.  Click to Zoom. Exterior parking lot at Bldg. 23 will be modified to meet code accessibility requirements.  Click to Zoom. Typical hallway were A/C systems at bathrooms will be upgraded. Click to Zoom.
Existing visitor restrooms at first floor restrooms need repairs.  Click to Zoom. Ventilation systems at lobby will be replaced and upgraded.  Click to zoom. First floor improvements to include drinking fountain and DSA barrier removal. Click to Zoom.

About This Project

Aliso Hall Building 23 is a student residential building erected in 1960 on a total area of 37,426 SF. The building is located at University Drive and is widely identified by its red brick exterior facade. The scope of work for this project includes a full ADA renovation of two first floor visitor restrooms together with A/C improvements to all three floor bathrooms and at the main lobby room. The project includes installation of new electrical, mechanical, plumbing and fire safety systems at this locations. Environmental abatement work will also be carried out.

This total estimated construction cost is $200,000 and the project will provide fresh ventilation (heating and cooling) and A/C systems in restrooms. The project is intended to start on June 2012 and be completed during the Summer break when students are not in the building.

Statistical Information

Construction start date:
June 2012
Expected completion date:
Sept 2012
Construction Cost:
$200,000
Total Project Cost: $250,000
Gross sq. footage:
10,000
Assignable sq. footage addition:
1,200
% of project complete:
0%

Project Funding

  • University Housing Services

Progress of Major Construction Activities

  • Detail design is completed and has been approved by the Division of State Architects (DSA).
  • Drawings have been submitted for approval to the Fire Marshal.
  • Mechanical design is completed.

Key/Critical Issues Currently Pending

  • Complete Division One of Bid documents
  • Coordinate with Procurement and bid out Construction documents towards Summer implementation.

Upcoming Utility or Other Interruptions

  • NA at this time.