Cal Poly Pomona

September 2010 Updates

Alamitos Hall - Bldg. 22 ADA Restroom Upgrade

Building 22 typical exterior brick façade along University Dr.  Click to Zoom. Exterior parking lot at Bldg. 22 is comprehensively upgraded to meet accessibility  requirements.  Click to Zoom. Demo and repair of damaged concrete sidewalks at Building 22. Click to Zoom.
New concrete sidewalks, stairs and  ramps at Alamitos Hall, Bldg. 22.  Click to Zoom. New interior plumbing infrastructure, tile  finishing and fixtures were added at all three floors.  Click to zoom. View of new shower room improvements. Swanstone walls, waterproofed ceilings, and individual floor drains were included. Click to Zoom.

About This Project

Alamitos Hall Building 22 is a student residential building erected in 1961 on a total area of 37,426 SF. The building is located at University Drive and is widely identified by its red brick exterior facade. The scope of work for this project includes a full ADA renovation of all eight (8) restrooms and shower rooms; a total of approximately 2,700 SF. It includes installing new electrical, mechanical, plumbing and fire safety systems. Environmental abatement work will also be carried out at these facilities.

This $1.79 million project will provide fresh ventilation and A/C systems in restrooms, as well as the complete finishing systems, including ceramic tiles and waterproof ceiling tiles. The project was started on June 14, 2010 and construction at the dormitories will be completed by September 15, 2010. Construction of additional exterior walkways and stairs will be implemented and completed during the same timeframe. .

Statistical Information

Construction start date:
June 14, 2010
Expected completion date:
Sept 2010
Construction Cost:
$1,377,000
Total Project Cost: $1,790,000
Gross sq. footage:
3,700
Assignable sq. footage addition:
2,700
% of project complete:
98%

Project Funding

  • University Housing Services

Progress of Major Construction Activities

  • The project is completed within the expected schedule. The Fire Marshal has approved on September 2, 2010 the new fire alarm system and related safety improvements.
  • Fresh ventilation has been installed at all eight restrooms. New lighting fixtures now employ motion sensors to improve energy consumption.
  • Complete new plumbing, mechanical and electrical infrastructure is completed at all floors.
  • Exterior sidewalks, ramps and the new parking lot are currently completed. New concrete surfaces were poured and placed on approximately 7500 SQF of the building surroundings.
    10,000 SQF of new ceramic tile floors and walls are now completed replacing old finishing materials.
  • Lobby upgrades including two visitor restrooms at first floor and A/C at TV room is completed.

Key/Critical Issues Currently Pending

  • Complete construction Punch List of new construction work and made necessary improvements.
  • American Air Balance to deliver the air balance report containing the HVAC applied efficiencies and capacities.
  • Assure punch list and 100% construction activities are completed prior to students arrival to the building.
  • Recording of Notice of Completion to the project is expected by September 14, 2010.
  • Finalize project documentation. Processing of final payment, change order and retention.