June 2010 Updates

Alamitos Hall - Bldg. 22 ADA Restroom Upgrade

Building 22 typical exterior brick façade along University Dr.  Click to Zoom. Exterior sidewalk and parking lot will be upgraded to meet accessibility requirements.  Click to Zoom. Ongoing demolition activities at Building 22. Click to Zoom.
Environmental abatement activities required for lobby HVAC improvements.  Click to Zoom. New plumbing infrastructure will be installed improving the Service Life of the building.  Click to zoom. View of proposed improvements. Walls, ceilings and  floors will  be renewed. New HVAC systems will be installed. Click to Zoom.

About This Project

Alamitos Hall Building 22 is a student residential building erected in 1961 on a total area of 37,426 SF. The building is located at University Drive and is widely identified by its red brick exterior facade. The scope of work for this project includes a full ADA renovation of all eight (8) restrooms and shower rooms; a total of approximately 2,700 SF. It includes installing new electrical, mechanical, plumbing and fire safety systems. Environmental abatement work will also be carried out at these facilities.

This $1.79 million project will provide fresh ventilation and A/C systems in restrooms, as well as the complete finishing systems, including ceramic tiles and waterproof ceiling tiles. The project was started on June 14, 2010 and construction at the dormitories will be completed by September 15, 2010. Construction of additional exterior walkways and stairs will be implemented and completed during the same timeframe. .

Statistical Information

Construction start date:
June 14, 2010
Expected completion date:
Sept 2010
Construction Cost:
$1,377,000
Total Project Cost: $1,790,000
Gross sq. footage:
3,700
Assignable sq. footage addition:
2,700
% of project complete:
15%

Project Funding

  • University Housing Services

Progress of Major Construction Activities

  • Environmental abatement activities were completed during the first week of activities.
  • Demolition activities are completed at 2nd and 3rd floors.
  • Plumbing and mechanical activities started at 2nd and 3rd floors and are currently ongoing.
  • Contractor has delivered six (6) project submittals.
  • Underground high voltage conduits were identified at the future parking lot and coordinated in the scope of work.

Key/Critical Issues Currently Pending

  • Contractor to quickly complete all project submittals allowing sufficient time for material purchases.
  • Contractor to carefully excavate at parking lot in the vicinity of existing high voltage underground conduits.
  • Contractor to start the parking lot ramps and sidewalk demolition activities.
  • Contractor to set detour signage and temporary pathways outside to Building 22.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.