Contents
Cal Poly Pomona

February 2010 Updates

Alamitos Hall - Bldg. 22 ADA Restroom Upgrade

Building 22 typical exterior brick façade along University Dr.  Click to Zoom. Existing parking  to accommodate  new DSA access parking. Click to Zoom. Surrounding  sidewalks to main entrance will be upgraded to meet accessibility requirements.  Click to Zoom.
Surrounding  sidewalks to main entrance will be upgraded to meet accessibility requirements.  Click to Zoom. Existing conditions:  shower units and ceilings show clear signs of leaking and corrosion. A main project goal  is to improve ventilation and replace all finishings. Click to zoom. View of proposed improvements. Walls, ceilings and  floors will  be renewed. New HVAC systems will be installed. Click to Zoom.

About This Project

Alamitos Hall Building 22. is a student residential building erected in 1961 on a total SF area of 37,426 SF. The building is located at University Dr. and is widely identified by its red brick exterior facade. The scope of work of this project includes a full ADA renovation of all 8 restrooms and shower rooms on approximately 2,700 square feet. It includes installing completely new electrical, mechanical, plumbing and fire safety systems. Environmental abatement work will also be carried out at these facilities.

This $1.79 million project will provide fresh ventilation and A/C systems in restrooms, as well as the complete finishing systems, including ceramic tiles and waterproof ceiling tiles. The project will be implemented beginning June 14th during the Summer Quarter vacation period. Construction at the dormitories will be completed by September 15th 2010. Construction of additional walkways and stairs will be implemented and completed during Christmas Break 2010.

Statistical Information

Construction start date:
June 14, 2010
Expected completion date:
Sept 2010
Construction Cost:
$1,377,000
Total Project Cost: $1,790,000
Gross sq. footage:
3,700
Assignable sq. footage addition:
2,700
% of project complete:
0%

Project Funding

  • University Housing Services

Progress of Major Construction Activities

  • Additional ADA parking spots at the building and the required path of travel from University Drive have been designed and included in the bid documents.
  • Project Architect has completed and submitted the 100% construction documents.
  • Construction documents have been approved for Code review and accessibility review.
  • Underground high voltage conduits were identified at the future parking lot and coordinated in the scope of work.
  • State Fire Marshal has approved the construction documents.
  • Drawings were submitted to DSA.

Key/Critical Issues Currently Pending

  • Bid advertisement and provide complete bid documentation to the Procurement office.
  • Receive and open bids by March 30, 2010.
  • Make sure bidders have capacity to implement fast track construction work within tight schedule.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.