December 2009 Updates

Alamitos Hall - Bldg. 22 ADA Restroom Upgrade

Building 22 typical exterior brick façade along University Dr.  Click to Zoom. Existing parking  to accommodate  new DSA access parking. Click to Zoom. Surrounding  sidewalks to main entrance will be upgraded to meet accessibility requirements.  Click to Zoom.
Accessible lockers will be available for disabled students. Click to Zoom. Existing conditions:  shower units and ceilings show clear signs of leaking and corrosion. A main project goal  is to improve ventilation and replace all finishings. Click to zoom. View of proposed improvements. Walls, ceilings and  floors will  be renewed. New HVAC systems will be installed. Click to Zoom.

About This Project

Alamitos Hall Building 22. is a student residential building erected in 1961 on a total SF area of 37,426 SF. The building is located at University Dr. and is widely identified by its red brick exterior facade. The scope of work of this project includes a full ADA renovation of all 8 restrooms and shower rooms on approximately 2,700 square feet. It includes installing completely new electrical, mechanical, plumbing and fire safety systems. Environmental abatement work will also be carried out at these facilities.

This $1.70 million project will provide fresh ventilation and A/C systems in restrooms, as well as the complete finishing systems, including ceramic tiles and waterproof ceiling tiles. The project will be implemented beginning June 14th during the Summer Quarter vacation period. Project will be completed by September 10th 2010.

In addition, the ground floor will require additional work to remove access barriers, provide access signage, and provide fully accessible restrooms for dormitories tenants.

Statistical Information

Construction start date:
June 14, 2010
Expected completion date:
Sept 2010
Construction Cost:
$1,379,000
Total Project Cost: $1,791,000
Gross sq. footage:
3,700
Assignable sq. footage addition:
2,700
% of project complete:
0%

Project Funding

  • Funding for this project is from University Housing a Department of Student Affairs Division utilizing existing reserve funds.

Progress of Major Construction Activities

  • A topographic plan has been developed in order to facilitate design of new DSA parking spots at the building and a required path of travel from University Drive.
  • Project Architect has delivered the 95% construction documents.
  • Construction documents has been sent to PC Associates for Code review and accessibility review.
  • Air balance report has been prepared for the existing conditions.

Key/Critical Issues Currently Pending

  • Identify and circumvent high voltage conduits at north parking lot.
  • Receive and complete back check code review.
  • Submit drawings to regulatory agencies including DSA and Fire Marshal.
  • Advertise Bid by February 2010 and coordinate process with the Procurement Office.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.