June 2009 Updates

Montecito Hall - Bldg. 21 ADA Restroom Upgrade

Building 20 typical exterior brick façade view along University Dr. Click to Zoom. Existing parking will be redesign to accommodate for new DSA parking spots. Click to Zoom. View of Montecito Hall  Bldg. 21  site during construction. Click to Zoom.
Existing piping have been abated and removed. Rough plumbing and electrical  activities have started at the site. Click to Zoom. New plumbing infrastructure is  installed as part of a comprehensive renewal of the building’s mechanical infrastructure.  Click to Zoom. Ceilings containing asbestos, as well as paint & tiles containing lead undergo environmental abatement removal before new  fixtures are installed. Click to Zoom.

About This Project

Montecito Hall Building 21. is a student residential building erected in 1961 on a total SF area of 37,426 SF. The building is located at University Dr. and is widely identified by its red brick exterior facade. The scope of work of this project includes a full ADA renovation of all 8 restrooms and shower rooms on approximately 2,700 square feet. It includes installing completely new electrical, mechanical, plumbing and fire safety systems. Environmental abatement work will also be carried out at these facilities.

This $1.52 million project will provide fresh ventilation and A/C systems in restrooms, as well as the complete finishing systems, including ceramic tiles and waterproof ceiling tiles. The project will be implemented beginning June 15th during the Summer Quarter vacation period. Project will be completed by September 10th 2009.

In addition, the ground floor will require additional work to remove access barriers, provide access signage, and provide fully accessible restrooms for dormitories tenants.

Statistical Information

Construction start date:
June 15, 2009
Expected completion date:
Sept 2009
Construction Cost:
$1,150,000
Total Project Cost: $1,500,000
Gross sq. footage:
3,700
Assignable sq. footage addition:
2,700
% of project complete:
15%

Project Funding

  • Funding for this project is from University Housing a Department of Student Affairs Division utilizing existing reserve funds.

Progress of Major Construction Activities

  • Abatement work, which started on Saturday, June 13, 2009, has been completed according to schedule during the first week of activities.
  • Demolition of four bathrooms at third and second floors is completed. Demolition at the first level is 75% completed.
  • Plumbing, electrical and HVAC submittals have been reviewed and approved.
  • Rough plumbing activities are undergoing at third and second floors.
  • Rough HVAC activities have started at the 3rd floor.
  • Existing rebar reinforcement at concrete slabs was identified using modern radar equipment prior to core drilling activities.

Key/Critical Issues Currently Pending

  • Accelerate plumbing activities at the site to comply with fast track schedule.
  • Complete submittals review process in order to accelerate the construction process. Particularly for long lead items such as new doors and “Swanstone” for finishing of shower room walls.
  • Trace and repair electrical conduits at unforeseen locations of the site.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.