May 2009 Updates

Montecito Hall - Bldg. 21 ADA Restroom Upgrade

Building 20 typical exterior brick façade view along University Dr. Click to Zoom. Existing parking will be redesign to accommodate for new DSA parking spots. Click to Zoom. Outdated telephone wall at main lobby will be redesign. Click to Zoom.
New wall partitions and duct work for the air conditioning system. Click to Zoom. Existing shower units show clear signs of leaking and corrosion. Ceilings will undergo abatement and will be modernized. Click to Zoom. New shower rooms with individual drains were installed in all six shower rooms. Click to Zoom.

About This Project

Montecito Hall Building 21. is a student residential building erected in 1961 on a total SF area of 37,426 SF. The building is located at University Dr. and is widely identified by its red brick exterior facade. The scope of work of this project includes a full ADA renovation of all 8 restrooms and shower rooms on approximately 2,700 square feet. It includes installing completely new electrical, mechanical, plumbing and fire safety systems. Environmental abatement work will also be carried out at these facilities.

This $1.52 million project will provide fresh ventilation and A/C systems in restrooms, as well as the complete finishing systems, including ceramic tiles and waterproof ceiling tiles. The project will be implemented beginning June 15th during the Summer Quarter vacation period. Project will be completed by September 10th 2009.

In addition, the ground floor will require additional work to remove access barriers, provide access signage, and provide fully accessible restrooms for dormitories tenants.

Statistical Information

Construction start date:
June 15, 2009
Expected completion date:
Sept 2009
Construction Cost:
$1,250,000
Total Project Cost: $1,600,000
Gross sq. footage:
3,700
Assignable sq. footage addition:
2,700
% of project complete:
0%

Project Funding

  • Funding for this project is from University Housing a Department of Student Affairs Division utilizing existing reserve funds.

Progress of Major Construction Activities

  • The low responsible bidder is Delt Builder with a low bid amount of $1,099,000.00
  • Contract documents have been signed by Contractor and approved by the Chancellor’s Office.
  • Procurement Office has issued the Notice to proceed. Construction to start on June 15, 2009.
  • A service agreement has been authorized for the environmental Contractor - Janus Corporation - to abate asbestos and lead at the site.
  • Preconstruction Meeting discussions were scheduled for Friday May 22nd.

Key/Critical Issues Currently Pending

  • Coordinate abatement work starting on Saturday June 13th at Bldg. 21. Environmental activities will include asbestos and lead abatement and require extensive coordination between Housing, General contractor and the abatement specialist.
  • Initiate submittal review process to accelerate the construction process.
  • Assure contractor protects new installed carpet at building while performing construction activities.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.