October 2008 Updates

Montecito Hall - Bldg. 21 ADA Restroom Upgrade

Building 20 typical exterior brick façade view along University Dr. Click to Zoom. Bldg. 20: New wall, bench and ADA drinking fountain at lobby. Click to Zoom. New wall partitions and duct work for the air conditioning system. Click to Zoom.
New cold and hot water piping is installed at. Click to Zoom. View of new lockers, lavatories and tile finishing. All new plumbing, HVAC and electrical was installed. Click to Zoom. New shower rooms with individual drains were installed in all six shower rooms. Click to Zoom.

About This Project

Montecito Hall Building 21. is a student residential building erected in 1961 on a total SF area of 37,426 SF. The building is located at University Dr. and is widely identified by its red brick exterior facade. The scope of work of this project includes a full ADA renovation of all 8 restrooms and shower rooms on approximately 2,700 square feet. It includes installing completely new electrical, mechanical, plumbing and fire safety systems. Environmental abatement work will also be carried out at these facilities.

This $1.52 million project will provide fresh ventilation and A/C systems in restrooms, as well as the complete finishing systems, including ceramic tiles and waterproof ceiling tiles. The project will be implemented beginning June 15th during the Summer Quarter vacation period. Project will be completed by September 10th 2009.

In addition, the ground floor will require additional work to remove access barriers, provide access signage, and provide fully accessible restrooms for dormitories tenants.

Statistical Information

Construction start date:
June 15, 2009
Expected completion date:
Sept 2009
Construction Cost:
$1,250,000
Total Project Cost: $1,520,000
Gross sq. footage:
3,700
Assignable sq. footage addition:
2,700
% of design project complete:
30%

Progress of Major Construction Activities

  • Service agreement with Architect has been issued by the Procurement Office.
  • Design team have walked the site on several occasions to identify and study the existing mechanical, electrical and Fire alarm infrastructure components.
  • Design phase is currently underway and 30% completed.

Key/Critical Issues Currently Pending

  • Complete 90% design by the end of November 2008.
  • Environmental abatement survey is required for the facilities.
  • Submit drawings to regulatory agencies including DSA and Fire Marshal.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.