Encinitas Hall - Bldg. 20 ADA Restroom Upgrade

Building 20 typical exterior brick façade view along University Dr. Click to Zoom. Bldg. 20 Interior Hallways.  1-16-2008. Click to Zoom. Existing doors will be ADA upgraded. Ceramic tiles renewed and new lockers installed. Click to Zoom. Corrosive ceilings will be replaced with modern waterproof systems. New a/c and ventilation systems will be installed. Click to Zoom.

About This Project

Encinitas Hall Building 20. is a student residential building erected in 1961 on a total SF area of 37,426 SF. The building is located at University Dr. and is widely identified by its red brick exterior facade. The scope of work of this project includes a full ADA renovation of all 8 restrooms and shower rooms on approximately 2,700 square feet. It includes installing completely new electrical, mechanical, plumbing and fire safety systems. Environmental abatement work will also be carried out at these facilities.

This $1.6 million project will provide fresh ventilation and A/C systems in restrooms, as well as the complete finishing systems, including ceramic tiles and waterproof ceiling tiles. The project will be implemented beginning June 16 th during the Summer Quarter vacation period. Project will be completed by September 8 th 2008.

In addition, the ground floor will require additional work to remove access barriers, provide access signage, and provide fully accessible restrooms for dormitories tenants.

Statistical Information

Construction start date:
June 2008
Expected completion date:
Sept 2008
Construction Cost:
$1,353,750
Total Project Cost: $1,683,000
Gross sq. footage:
3,700
% of project complete:
0%

Progress of Major Construction Activities

  • 100 % working documents phase completed
  • Bid documents completed
  • Bid Conference and Contractor’s Job Walk scheduled for 2.27.08

Key/Critical Issues Currently Pending

  • Bid Opening scheduled for 3.25.08
  • Verify Contractor’s qualification and Bid dollar amounts
  • Time sensitive project implementation requires strict planning and scheduling of construction activities

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.