Contents
Cal Poly Pomona

November 2011 Updates

Kellogg Arabian Horse Library

New Lobby Entrance. Click to Zoom. Interior View - Collection Area. Click to Zoom. WK Kellogg Sculpture. Click to Zoom.
WK Kellogg Sculpture. Click to Zoom. Floor Plan with Proposed Shelving and Furniture. Click to Zoom. Reflected Ceiling Plan. Click to Zoom.

About This Project

The WK Kellogg Arabian Horse Library special collection, which is currently partially housed in the Kellogg Stables building, will now be located in the University Library first floor room 1832.  The entry to the 5,200 GSF space will be located at the main entry lobby of the University Library, adjacent to Starbucks. The entry has been designed to identify this special Library space and provide patrons the opportunity to view the historical artifacts. The collection includes numerous archival materials which requires special lighting (UV protection) and mechanical system (s) to control humidity and temperature, these program elements have been addressed in the design and construction of the new space.

Statistical Information

Construction start date:
April 2011
Expected completion date:
August 2011
Construction Cost:
$0
Total Project Cost: $1,895,000
Gross sq. footage:
5,200
Assignable sq. footage:
0
% of project complete:
99%

Project Funding

  • By donations from the Kellogg Foundation.

Progress of Major Construction Activities

  • HVAC system testing and balancing underway, commissioning complete, minor punch list items being addressed.
  • Punch list corrections ongoing, few remaining items.
  • Shelving installation complete.
  • Library staff placed large amount of collection.
  • Kellogg wall sculpture installed.

Key/Critical Issues Currently Pending

  • Installation of CPP Horse Photo wall covering, compatibility of photograph file issues being reviewed/addressed.

Upcoming Utility or Other Interruptions

  • NA at this time.

Other Areas of Significance

  • NA at this time.