September 2011 Updates

Kellogg Arabian Horse Library

Interior view - New Lobby Extension. Click to Zoom. Interior View - Collection Area. Click to Zoom. Construction, casework installation. Click to Zoom.
Construction, painting and ceiling  installation. Click to Zoom. Floor Plan with Proposed Shelving and Furniture. Click to Zoom. Reflected Ceiling Plan. Click to Zoom.

About This Project

The WK Kellogg Arabian Horse Library special collection, which is currently partially housed in the Kellogg Stables building, will now be located in the University Library first floor room 1832.  The entry to the 5,200 GSF space will be located at the main entry lobby of the University Library, adjacent to Starbucks. The entry has been designed to identify this special Library space and provide patrons the opportunity to view the historical artifacts. The collection includes numerous archival materials which requires special lighting (UV protection) and mechanical system (s) to control humidity and temperature, these program elements have been addressed in the design and construction of the new space.

Statistical Information

Construction start date:
April 2011
Expected completion date:
August 2011
Construction Cost:
$0
Total Project Cost: $1,895,000
Gross sq. footage:
5,200
Assignable sq. footage:
0
% of project complete:
95%

Project Funding

  • By donations from the Kellogg Foundation.

Progress of Major Construction Activities

  • HVAC system testing and balancing underway, commissioning scheduled for early October.
  • Punch list corrections ongoing.
  • State Fire Marshall Certificate of Occupancy issued.
  • Shelving installation ongoing.
  • Furniture to be installed mid October.
  • Library staff scheduled to begin shelving the collection October 18.
  • Kellogg wall sculpture scheduled to be installed

Key/Critical Issues Currently Pending

  • HVAC system start up and commissioning.
  • Installation of CPP Horse Photo wall covering, compatibility of photograph file issues being reviewed/addressed.

Upcoming Utility or Other Interruptions

  • During construction the lobby door to Starbucks will be closed during specific time frames.

Other Areas of Significance

  • NA at this time.