Contents
Cal Poly Pomona

Lower Reservoir Replacement at Northwest Quadrant

Lower Reservoir at the Northwest Quadrant without previously existing cover. 1-16-2008. Click to Zoom. Floor conditions at existing Reservoir. 1-16-2008. Click to Zoom.
Lower Reservoir Equipment Room. 1-16-2008. Click to Zoom. Some electrical devices in the Lower Reservoir Equipment Room. 1-16-2008. Click to Zoom.

Photo of Leatha Elsdon
Leatha Elsdon
Sr. Project Manager

This project scope of work is currently under review. The overall design intent should be finalized within the next few weeks. Primary intent of this project is to improve the campus domestic water system infrastructure.

Questions or comments may be directed to the Project Manager, Leatha Elsdon at ljesldon@csupomona.edu.

Construction start date: June 2008
Expected completion date: March 2009
Construction Cost: TBD
Total Project Cost: $1,515,000
Gross square footage: N/A
Assignable sq. footage: N/A

Updates