Fire Alarm Upgrades - Various Buildings

Building 46  Look above the drop ceiling. 7-17-2007. Click to Zoom. Building 1  New Fire Control Panel. 7-27-2007. Click to Zoom.
Building 9  New Pull Station vs. Old Pull Station. 8-28-2007. Click to Zoom. Building 13  Abatement Activities. 12-19-2007. Click to Zoom.

Photo of Robert Rice
Robert Rice
Project Coordinator

The Fire Alarm Upgrades project consists of engineering and designing a new system that complies with all current applicable standards and codes, communicates and integrates with other campus fire alarm systems and any potential future fire alarm related upgrades. The buildings being upgraded are 1, 2, 6, 9, 13, 25, 29, 41, 43 and 46. Due to good results, Buildings 67, 89 and 92 have been added to the Fire Alarm Upgrades for this year. There is also consideration on reprogramming the Fire Alarm System in Building 4. Last year, Buildings 7, 8 and 45 were completed.

Questions or comments may be directed to the Project Coordinator, Robert Rice at rjrice@csupomona.edu

Construction start date: April 19, 2007
Expected completion date: Summer 2008
Construction Cost: TBD
Total Project Cost: $1,900,000
Gross square footage: 643,860
Assignable sq. footage: 389,322