Building 22 typical exterior brick façade along University Dr. Click to Zoom. Existing parking  to accommodate  new DSA access parking. Click to Zoom.
Accessible lockers will be available for disabled students. Click to Zoom. View of proposed improvements. Walls, ceilings and  floors will  be renewed. New HVAC systems will be installed. Click to Zoom.

Photo of Jaime Landman
Jamie Landman
Project Manager

amitos Hall Building 22 is a student residential building erected in 1961 on a total area of 37,426 SF. The building is located at University Drive and is widely identified by its red brick exterior facade. The scope of work for this project includes a full ADA renovation of all eight restrooms and shower rooms; a total of approximately 2,700 SF. It includes installing new electrical, mechanical, plumbing and fire safety systems. Environmental abatement work will also be carried out at these facilities.

This $1.55M project will provide fresh ventilation and A/C systems in restrooms, as well as the complete finishing systems, including ceramic tiles and waterproof ceiling tiles. The project was started on June 14, 2010 and construction at the dormitories will be completed by September 15, 2010. Construction of additional exterior walkways and stairs will be implemented and completed during the same timeframe.

Questions or comments may be directed to the Project Manager, Jamie Landman at jlandman@csupomona.edu

Construction start date:
June 14, 2010
Expected completion date:
Sept 2010
Construction Cost:
$1,225,000
Total Project Cost: $1,550,000
Gross sq. footage:
10,000
Assignable sq. footage addition:
2,700

Project Funding

  • Funding for this project is from University Housing a Department of Student Affairs Division utilizing existing reserve funds.