Encinitas Hall Building 20. is a student residential building erected in 1961 on a total SF area of 37,426 SF. The building is located at University Dr. and is widely identified by its red brick exterior facade. The scope of work of this project includes a full ADA renovation of all 8 restrooms and shower rooms on approximately 2,700 square feet. It includes installing completely new electrical, mechanical, plumbing and fire safety systems. Environmental abatement work will also be carried out at these facilities.

This $1.6 million project will provide fresh ventilation and A/C systems in restrooms, as well as the complete finishing systems, including ceramic tiles and waterproof ceiling tiles. The project will be implemented beginning June 16 th during the Summer Quarter vacation period. Project will be completed by September 8 th 2008.

In addition, the ground floor will require additional work to remove access barriers, provide access signage, and provide fully accessible restrooms for dormitories tenants.

Questions or comments may be directed to the Project Manager, Jamie Landman at jlandman@csupomona.edu

Construction start date: June 2008
Expected completion date: Sept 2008
Construction Cost: $1,353,750
Total Project Cost: $1,683,000
Gross square footage: 3,700
Status: Complete